Project

General

Profile

Activity

From 04/29/2011 to 05/28/2011

05/09/2011

12:53 PM Feature #110 (In Progress): [pre-rollout] prepare data & tools for load test
chin-yeh

05/05/2011

12:13 PM Feature #110 (Closed): [pre-rollout] prepare data & tools for load test
prepare the following items which are needed by load test:
* list of performance metrics, e.g. expected time, time t...
chin-yeh
11:40 AM Feature #108 (Closed): [pre-rollout] [production] clone USA db
clone the USA database.
update shopper table to point all email to a dummy email address
chin-yeh
11:39 AM Feature #107 (Closed): [pre-rollout] [production] clone US mall application
clone the US mall application which needed for load test or UAT chin-yeh
11:35 AM Feature #106 (Closed): [pre-rollout] [production] duplicate STORE db schema
duplicate the *STORE* database schema and export the data which needed for load test chin-yeh
 

Also available in: Atom