Project

General

Profile

Activity

From 08/21/2010 to 09/19/2010

09/02/2010

02:17 PM QConnector_ProjectPlan_rev_PA2.pdf
Revision PA2 - Revised the prototype timeline. Chooi-Mey

08/23/2010

09:46 AM QConnector_ProjectPlan_PA1.pdf
Chooi-Mey
09:46 AM Document: Project Plan
Initial Project Plan. To be revised after prototype complete develop and tested. Chooi-Mey
09:21 AM aSyncWebService.uml
Chooi-Mey
09:21 AM InterfaceAdaptor_part2.jpg
Chooi-Mey
09:21 AM InterfaceAdaptor_part1.jpg
Chooi-Mey
09:21 AM Document: Activity Diagram
Describes the activity flow of the system. Chooi-Mey
 

Also available in: Atom